networks year12 standard

📖 Prior Knowledge

ContentPrior knowledgeUsed for
Networks, Paths Trees- graph diagrams- critical path analysis

Critical path analysis

  • Construct a network diagram from a precedence table or equivalent, including those involving dummy activities, limited to 10 activities
  • Explain the term critical path
  • Apply forward and backward scanning to determine the earliest starting time (EST) and latest starting time (LST) for each activity in a project
  • Calculate float times to identify critical and non-critical activities
  • Analyse ESTs and LSTs to locate the critical path(s) for the project
  • Apply critical path analysis to determine the minimum completion time for a project
  • Construct a Gantt chart to represent a project from a network diagram indicating the critical path
  • Examine the impact of increasing or reducing the duration of an activity on the completion time of the project or task being modelled
  • Use a spreadsheet to model a project involving precedence tables and solve related problems